In a landmark ruling on real estate contract termination in Dubai, the Court of Cassation issued Judgment in Case 197/2025 concerning the legal characterization and consequences of earnest money in property sale contracts.
Background of the Dispute
The dispute arose from a real estate sale contract executed in November 2023 concerning a parcel of land located in Dubai. The total purchase price was agreed at AED 6,750,000, of which AED 675,000 was paid as an upfront amount described contractually as earnest money. The balance was to be settled no later than 13 January 2024.
The purchaser failed to complete payment of the remaining amount within the contractual deadline, including an additional extension period provided under the supplementary terms. Consequently, the seller-initiated proceedings before the Dubai Court of First Instance seeking termination of the sale contract and retention of the earnest money in accordance with the contractual provisions.
The Court of First Instance ruled in favour of the seller, ordering termination of the contract and awarding AED 540,000 (representing 8% of the property value as contractually agreed) in addition to legal interest. The judgment was upheld on appeal. The purchaser subsequently filed a cassation challenge, alleging misapplication of the law, lack of proper reasoning, and absence of proven damages.
Legal Issue Before the Court of Cassation
The central issue before the Court of Cassation concerned the legal characterization of the earnest money and whether the seller was entitled to retain part of it without demonstrating actual damage.
The purchaser argued that:
- Once the contract was terminated, no penalty should be payable.
- The seller had not suffered actual damage, especially given that property values had allegedly increased.
- The purchaser had acted in good faith and requested additional time to complete payment.
The Court rejected these arguments.
The Court’s Legal Reasoning
The Court reaffirmed several key legal principles:
1. Authority of the Trial Court in Contract Interpretation
The Court emphasized that trial courts have full discretion to interpret contracts, determine their legal nature, and ascertain the true intention of the parties. What governs is the substance and mutual intention—not merely the labels used by the parties.
Such findings are subject to cassation review only where there is misapplication of law, not where there is a factual reassessment.
2. Legal Nature of Earnest Money Under Article 148
The Court relied on Article 148 of the UAE Civil Transactions Law, which governs earnest money. It clarified that:
- Earnest money is typically paid at the time of concluding a sale contract.
- Although payment of earnest money generally indicates that the contract is final and binding, the parties may agree that it serves as consideration for a right of withdrawal.
- Where the contract expressly grants both parties the option to withdraw against forfeiture or repayment of the earnest money (double in the case of seller withdrawal), the earnest money functions as a contractual mechanism for optional rescission.
In such cases:
- If the purchaser withdraws, he forfeits the earnest money.
- If the seller withdraws, he must refund the earnest money and pay an equivalent amount.
- The amount is payable irrespective of actual damage.
- Unlike a penalty clause, earnest money in this context cannot be reduced or cancelled by the court due to lack of damage.
The Court made a crucial distinction: the obligation arising from earnest money is not compensation for damage but the agreed consideration for exercising the right of withdrawal.
3. Application to the Present Case
The contract contained explicit clauses providing that:
- If the purchaser failed to complete payment within the agreed timeframe for reasons within his control, the seller could terminate the contract and retain the earnest money.
- If the seller withdrew, he would be liable to refund the earnest money and pay an equivalent amount.
The Court concluded that this structure clearly reflected a sale contract accompanied by an option of withdrawal secured by earnest money.
It was undisputed that:
The purchaser failed to settle the remaining price within the contractual and extended deadlines.
There was no written agreement extending the deadline beyond what was contractually provided.
Payment of the purchase price was a prior obligation to transfer of title.
Therefore, the purchaser was in contractual breach. The seller was entitled to terminate the contract and retain the agreed percentage (8%) as stipulated in the supplementary conditions.
The Court further confirmed that the seller was not required to prove actual loss in order to retain the earnest money.
Cassation Court’s Conclusion
The Court of Cassation held that the lower courts had:
- Correctly interpreted the contract;
- Properly characterized the earnest money;
- Applied Article 148 of the Civil Transactions Law;
- Issued a reasoned judgment supported by the record.
The cassation challenge amounted merely to a dispute over factual appreciation and contractual interpretation—matters falling within the discretion of the trial court.
Accordingly, the Court rejected the appeal and ordered the appellant to bear costs and legal fees.
Practical Implications for Real Estate Transactions
This judgment carries significant implications for property developers, investors, brokers, and purchasers in Dubai:
Earnest money clauses must be carefully drafted. The intention of the parties—whether the amount is part of the price or consideration for withdrawal—will determine its legal effect.
Earnest money differs from a penalty clause. Unlike penalty clauses, earnest money tied to a right of withdrawal is generally not subject to judicial reduction for lack of damage.
Deadlines must be strictly observed. Where the contract requires written extension agreements, informal communications or good-faith intentions will not suffice.
Payment obligations may precede transfer obligations. Failure to fulfill the purchaser’s payment obligation can justify termination even if title transfer has not yet occurred.
Market fluctuations are irrelevant. An increase in property value does not negate contractual entitlement to earnest money.
Conclusion
The Dubai Court of Cassation has reaffirmed the binding nature of contractual earnest money provisions in real estate transactions. The ruling underscores the importance of contractual precision and strict compliance with agreed timelines.
In a dynamic property market such as Dubai’s, this decision serves as a reminder that courts will enforce the contractual allocation of risk and consequences agreed by the parties—even in the absence of proven loss.
For investors and developers alike, clarity in drafting and discipline in execution remain paramount.
If you require further clarification or legal assistance concerning the matters discussed in this article, please do not hesitate to contact Khairallah Advocates & Legal Consultants LLC. Our lawyers would be happy to assist you.
Authors:



